Registry
Commercial
New commercial building (ground-up)
New commercial, office, retail, industrial or institutional building — shell and/or full build.
partialHB 803: n/areviewed never
Who can pull the permit
- CGCCertified General Contractor
- CBCCertified Building Contractor
Subs under the prime's permit: EC, ER, CFC, RF, CAC, CMC, RA, CCC, RC, SPEC-EXCAVATION, SPEC-CONCRETE, NONE
Decision — first matching row wins
| # | When | Permit | Type | Reason |
|---|---|---|---|---|
| 1 | otherwise | yes | Building — New Commercial (full plan review: architectural, structural, MEP, fire, accessibility, site/ROW) | Ground-up commercial construction requires full plan review under the FBC (signed & sealed architectural, structural and MEP), fire-district review, FBC-Accessibility (Ch. 11 / FBC-A), site development / SFWMD, ROW and utility connections, plus impact/mobility fees. A CBC is limited to ≤ 3 stories; taller or unlimited needs a CGC. |
Inputs the rule needs
- sqftBuilding area (sq ft)
- storiesStories
- occupancyOccupancy group (if known)
Documents (base)
- Owner authorization / signed permit application (owner or agent signature, notarized where the authority requires)
- Signed & sealed architectural, structural, mechanical, electrical, plumbing, energy (FBC-EC) and fire drawings
- Site plan / survey showing property lines, setbacks, easements, septic and the proposed work with drainage, parking, ADA routes, landscaping and utilities
- Florida Product Approvals for envelope, roofing, glazing, shutters
- Fire sprinkler / alarm drawings (deferred submittal ok)
- Accessibility (FBC-A) compliance
- Site development / SFWMD ERP; ROW and utility connection permits; impact & mobility fee worksheet
- Notice of Commencement — recorded with the Clerk of Court and a certified copy (or notarised statement of filing) given to the building department BEFORE the first inspection. Statutory floor is a direct contract over $5,000 (FS 713.135(1)(e)); HVAC repair/replace under $15,000 exempt; lien-law protection applies above $2,500 (FS 713.02(5)). Authorities differ: Collier applies $2,500 (Bulletin B-44, pool checklist) and charges a $5 NOC admin fee; Lee will not ISSUE the permit until the NOC is recorded ($5,000+); Fort Myers, Bonita, Fort Myers Beach $5,000; Marco Island / Sanibel per statute (posted on site before first inspection)
- Contractor registration current with the county (license, GL insurance, workers' comp or exemption on file)