Concrete slab / equipment pad (AC, generator, shed pad)

Stand-alone slab not part of a larger permitted structure's scope.

inferredHB 803: eligiblereviewed never

Who can pull the permit

  • SPEC-CONCRETEConcrete Forming & Placing (county specialty)
  • CGCCertified General Contractor
  • CBCCertified Building Contractor
  • CRCCertified Residential Contractor
  • NONENo contractor license
  • OWNER-BUILDEROwner-occupied 1–2 family (FS 489.103(7))

Decision — first matching row wins

#WhenPermitTypeReason
1supports_equipment is yesconditionalOften covered by the equipment's own mechanical/electrical permitA small equipment pad poured as part of an HVAC change-out or generator install is typically covered under that trade permit, not a stand-alone building permit — but a pad poured well ahead of the equipment install, on spec, may need its own review. Reviewer to confirm per authority.
2otherwiseconditionalOften exempt as flatwork; a shed pad may be swept into the shed's own permitA stand-alone slab with no structure and no equipment on it is commonly treated like driveway/patio flatwork (see that job type) — exempt in some authorities, permitted in others above a size threshold. A pad specifically for a shed follows that shed's own permit requirement (see Shed).

Inputs the rule needs

  • sqftSlab area (sq ft)
  • supports_equipmentSupporting mechanical/electrical equipment (AC condenser, generator)?

Documents (base)

  1. Site plan / survey showing property lines, setbacks, easements, septic and the proposed work
  2. Contractor registration current with the county (license, GL insurance, workers' comp or exemption on file)

Sources