Fuel dispenser / gas station / above-ground tank (commercial)
Motor-fuel dispensing, canopy, USTs/ASTs, EV DC fast charging at scale.
inferredHB 803: n/areviewed never
Who can pull the permit
- CGCCertified General Contractor
- CBCCertified Building Contractor
- ECCertified Electrical Contractor
- ERRegistered Electrical Contractor
- CFCCertified Plumbing Contractor
- RFRegistered Plumbing Contractor
Decision — first matching row wins
| # | When | Permit | Type | Reason |
|---|---|---|---|---|
| 1 | otherwise | yes | Building + Fire + FDEP (storage tanks) — Motor Fuel Facility | Fuel facilities stack building, fire-code (flammable/combustible liquids), FDEP storage-tank registration/permitting, electrical (hazardous classified locations) and environmental review. |
Documents (base)
- Owner authorization / signed permit application (owner or agent signature, notarized where the authority requires)
- Signed & sealed civil/structural/MEP
- Fire-code plan (NFPA 30/30A)
- FDEP storage-tank registration & secondary containment
- Hazardous-location electrical
- Notice of Commencement — recorded with the Clerk of Court and a certified copy (or notarised statement of filing) given to the building department BEFORE the first inspection. Statutory floor is a direct contract over $5,000 (FS 713.135(1)(e)); HVAC repair/replace under $15,000 exempt; lien-law protection applies above $2,500 (FS 713.02(5)). Authorities differ: Collier applies $2,500 (Bulletin B-44, pool checklist) and charges a $5 NOC admin fee; Lee will not ISSUE the permit until the NOC is recorded ($5,000+); Fort Myers, Bonita, Fort Myers Beach $5,000; Marco Island / Sanibel per statute (posted on site before first inspection)
- Contractor registration current with the county (license, GL insurance, workers' comp or exemption on file)