Kitchen / bath remodel with plumbing or electrical changes

Relocating fixtures, adding circuits, moving drains.

partialHB 803: excludedreviewed never

Who can pull the permit

  • CGCCertified General Contractor
  • CBCCertified Building Contractor
  • CRCCertified Residential Contractor
  • OWNER-BUILDEROwner-occupied 1–2 family (FS 489.103(7))

Subs under the prime's permit: CFC, RF, EC, ER

Decision — first matching row wins

#WhenPermitTypeReason
1otherwiseyesBuilding — Remodel (with plumbing/electrical sub-permits)Relocating plumbing or electrical is permitted work; a Division I contractor pulls the master and trades pull subs, or trades pull stand-alone permits for trade-only scope.

Documents (base)

  1. Owner authorization / signed permit application (owner or agent signature, notarized where the authority requires)
  2. Plan showing existing/proposed fixtures and circuits
  3. Notice of Commencement — recorded with the Clerk of Court and a certified copy (or notarised statement of filing) given to the building department BEFORE the first inspection. Statutory floor is a direct contract over $5,000 (FS 713.135(1)(e)); HVAC repair/replace under $15,000 exempt; lien-law protection applies above $2,500 (FS 713.02(5)). Authorities differ: Collier applies $2,500 (Bulletin B-44, pool checklist) and charges a $5 NOC admin fee; Lee will not ISSUE the permit until the NOC is recorded ($5,000+); Fort Myers, Bonita, Fort Myers Beach $5,000; Marco Island / Sanibel per statute (posted on site before first inspection)
  4. Contractor registration current with the county (license, GL insurance, workers' comp or exemption on file)