Whole building

New single-family house (ground-up)

New residence on a lot: site work, structure, MEP subs, driveway, septic/well or utility connections.

partialHB 803: excludedreviewed never

Who can pull the permit

  • CGCCertified General Contractor
  • CBCCertified Building Contractor
  • CRCCertified Residential Contractor
  • OWNER-BUILDEROwner-occupied 1–2 family (FS 489.103(7))

Subs under the prime's permit: EC, ER, CFC, RF, CAC, CMC, RA, CCC, RC, CPC, RP, SPEC-EXCAVATION, SPEC-CONCRETE, SPEC-PAVER, SPEC-ALUMINUM, SPEC-FENCE, NONE

Decision — first matching row wins

#WhenPermitTypeReason
1otherwiseyesBuilding — New Single-Family Residence (with site, ROW, MEP sub-permits)New construction always requires a building permit; expect parallel site/ROW review, impact fees, DOH septic/well permits where applicable, and environmental clearance for clearing (see the environmental screen).

Inputs the rule needs

  • septicSeptic (vs. county sewer)?
  • wellPrivate well (vs. county water)?
  • acresLot size (acres)
  • clearingNative vegetation being cleared beyond the building envelope?

Documents (base)

  1. Owner authorization / signed permit application (owner or agent signature, notarized where the authority requires)
  2. Signed & sealed architectural + structural + truss drawings; energy calcs (FBC-EC); wind-load design (ASCE 7)
  3. Site plan / survey showing property lines, setbacks, easements, septic and the proposed work with drainage/grading, driveway, septic/well, clearing limits
  4. Florida Product Approvals for openings, roofing, shutters
  5. DOH septic (OSTDS) construction permit / well permit if not on utilities
  6. Right-of-way / driveway connection permit
  7. Impact fee worksheet; school concurrency where required
  8. Vegetation removal / listed-species clearance where native habitat is disturbed
  9. Notice of Commencement — recorded with the Clerk of Court and a certified copy (or notarised statement of filing) given to the building department BEFORE the first inspection. Statutory floor is a direct contract over $5,000 (FS 713.135(1)(e)); HVAC repair/replace under $15,000 exempt; lien-law protection applies above $2,500 (FS 713.02(5)). Authorities differ: Collier applies $2,500 (Bulletin B-44, pool checklist) and charges a $5 NOC admin fee; Lee will not ISSUE the permit until the NOC is recorded ($5,000+); Fort Myers, Bonita, Fort Myers Beach $5,000; Marco Island / Sanibel per statute (posted on site before first inspection)
  10. Contractor registration current with the county (license, GL insurance, workers' comp or exemption on file)