Parking lot — new, resurface, restripe, seal

Commercial parking construction, resurfacing, striping or sealcoating.

inferredHB 803: n/areviewed never

Who can pull the permit

  • CGCCertified General Contractor
  • CBCCertified Building Contractor
  • SPEC-PAVERPaving / Paver Installation (county specialty)
  • SPEC-CONCRETEConcrete Forming & Placing (county specialty)
  • NONENo contractor license

Decision — first matching row wins

#WhenPermitTypeReason
1new_or_expand is yesyesSite / Paving Permit (drainage, ADA stalls, landscaping)New or expanded parking is site work: stormwater/drainage, ADA-compliant accessible stalls and routes, landscaping and lighting are reviewed; SFWMD ERP for larger impervious area.
2otherwiseconditionalRestripe/seal often needs only an ADA-compliance check; confirm locallySealcoating and restriping an existing lot is commonly light-touch, but re-striping must restore compliant ADA stalls and counts — Fort Myers explicitly lists parking-lot restriping/sealcoating as requiring a permit. Confirm per authority.

Inputs the rule needs

  • new_or_expandNew lot or expansion (vs. restripe/seal only)?required

Documents (base)

  1. Owner authorization / signed permit application (owner or agent signature, notarized where the authority requires)
  2. Site/paving & drainage plan; ADA stall layout
  3. SFWMD ERP for larger impervious area
  4. Contractor registration current with the county (license, GL insurance, workers' comp or exemption on file)