Cleared
Registry

Pools

New in-ground swimming pool / spa

New residential pool or spa, including the excavation, shell, equipment, deck and barrier.

partialHB 803: excludedreviewed never

Who can pull the permit

  • CPCCertified Commercial Pool/Spa Contractor
  • RPCertified Residential Pool/Spa Contractor
  • CGCCertified General Contractor
  • CBCCertified Building Contractor
  • CRCCertified Residential Contractor
  • OWNER-BUILDEROwner-occupied 1–2 family (FS 489.103(7))

Subs under the prime's permit: SPEC-EXCAVATION, SPEC-CONCRETE, SPEC-PAVER, SPEC-ALUMINUM, SPEC-SCREEN, SPEC-FENCE, EC, ER, CFC, RF, NONE

Decision — first matching row wins

#WhenPermitTypeReason
1residential = "com"yesBuilding — Commercial Pool/SpaCommercial pools require a building permit AND Florida Department of Health public-pool approval; only a CPC (not RP) may contract.
2otherwiseyesBuilding — Residential Pool/Spa (with electrical sub-permit)A new in-ground pool is a structure under FBC §105.1; no exemption applies. The pool contractor pulls the master permit; the electrical bonding/equipment circuit is a sub-permit pulled by an EC/ER.

Inputs the rule needs

  • residentialResidential (1–2 family) or commercial?required
  • spaIncludes a spa / hot tub?
  • screenScreen enclosure in the same contract?
  • septicProperty on septic?
  • depth_ftDeepest point (ft)

Per-authority differences

  • collier-unincorporatedBuilding Permit — Residential Pool via CityView ($100 application + $110 per inspection, Res. 2025-231; gas, electrical, fence and aluminum-screen contractors each pull their own sub-permit)
  • cape-coral
  • lee-unincorporatedResidential Pool/Spa Building Permit via eConnect

Documents (base)

  1. Owner authorization / signed permit application (owner or agent signature, notarized where the authority requires)
  2. Site plan / survey showing property lines, setbacks, easements, septic and the proposed work — pool, deck and equipment pad with setbacks dimensioned
  3. Signed & sealed pool engineering (shell, steel schedule, hydrostatic relief) — FBC-R Ch. 45 / ANSI/APSP-5
  4. Barrier compliance sheet — FS 515: fence/screen with self-closing gates OR approved alarms/covers
  5. Electrical: bonding grid & equipment layout (sub-permit by EC/ER)
  6. Product approvals for screen enclosure if included
  7. Notice of Commencement — recorded with the Clerk of Court and a certified copy (or notarised statement of filing) given to the building department BEFORE the first inspection. Statutory floor is a direct contract over $5,000 (FS 713.135(1)(e)); HVAC repair/replace under $15,000 exempt; lien-law protection applies above $2,500 (FS 713.02(5)). Authorities differ: Collier applies $2,500 (Bulletin B-44, pool checklist) and charges a $5 NOC admin fee; Lee will not ISSUE the permit until the NOC is recorded ($5,000+); Fort Myers, Bonita, Fort Myers Beach $5,000; Marco Island / Sanibel per statute (posted on site before first inspection)
  8. Contractor registration current with the county (license, GL insurance, workers' comp or exemption on file)

Sources