Mechanical / Electrical / Plumbing

Rooftop solar PV

Photovoltaic array with interconnection.

partialHB 803: excludedreviewed never

Who can pull the permit

  • ECCertified Electrical Contractor
  • ERRegistered Electrical Contractor
  • SPEC-SOLARSolar (state CVC / county specialty)
  • CGCCertified General Contractor
  • CBCCertified Building Contractor
  • CRCCertified Residential Contractor
  • OWNER-BUILDEROwner-occupied 1–2 family (FS 489.103(7))

Decision — first matching row wins

#WhenPermitTypeReason
1otherwiseyesBuilding (structural) + ElectricalPV requires structural review of the roof attachment (wind uplift) and electrical permit; utility interconnection is separate.

Documents (base)

  1. Owner authorization / signed permit application (owner or agent signature, notarized where the authority requires)
  2. Signed & sealed structural + electrical drawings
  3. Product approvals for racking
  4. Notice of Commencement — recorded with the Clerk of Court and a certified copy (or notarised statement of filing) given to the building department BEFORE the first inspection. Statutory floor is a direct contract over $5,000 (FS 713.135(1)(e)); HVAC repair/replace under $15,000 exempt; lien-law protection applies above $2,500 (FS 713.02(5)). Authorities differ: Collier applies $2,500 (Bulletin B-44, pool checklist) and charges a $5 NOC admin fee; Lee will not ISSUE the permit until the NOC is recorded ($5,000+); Fort Myers, Bonita, Fort Myers Beach $5,000; Marco Island / Sanibel per statute (posted on site before first inspection)
  5. Contractor registration current with the county (license, GL insurance, workers' comp or exemption on file)