Sump pump / sewage lift station

Below-grade drainage or sewage ejector pump system.

inferredHB 803: excludedreviewed never

Who can pull the permit

  • CFCCertified Plumbing Contractor
  • RFRegistered Plumbing Contractor
  • ECCertified Electrical Contractor
  • ERRegistered Electrical Contractor
  • CGCCertified General Contractor
  • CBCCertified Building Contractor
  • CRCCertified Residential Contractor
  • OWNER-BUILDEROwner-occupied 1–2 family (FS 489.103(7))

Decision — first matching row wins

#WhenPermitTypeReason
1otherwiseyesPlumbing + Electrical PermitA sewage lift/ejector station is plumbing work tied to the sanitary system (and, if it discharges to a septic system, needs DOH awareness); the pump's dedicated circuit and any alarm panel are electrical work. A stormwater sump serving only groundwater/foundation drainage still needs the electrical permit for its circuit.

Inputs the rule needs

  • sewageSewage ejector (vs. stormwater/groundwater sump)?

Documents (base)

  1. Plumbing + electrical permit applications with pump spec
  2. Contractor registration current with the county (license, GL insurance, workers' comp or exemption on file)

Sources